# December 2026 Security of Payment deadlines — when a payment claim served before Christmas is due (Australia)

A payment claim served in late November or December does not have a single national due date. Each state and territory Security of Payment Act counts its own business or working days, and the Christmas and New Year exclusions are not the same:

- **NSW, South Australia, Tasmania and the ACT** exclude 27–31 December (even when those days are not otherwise public holidays).
- **Victoria, Queensland and Western Australia** exclude the longer window from 22 December to 10 January inclusive.
- **The Northern Territory** excludes 25 December to 7 January inclusive, and counts _working days_ rather than business days. It uses a notice of dispute, not an East Coast-style payment schedule.
- **Part-day Christmas Eve and New Year’s Eve** (7pm to midnight) are counted as business or working days in South Australia and the Northern Territory. 31 December is still excluded in both places by the shutdown window. 24 December 2026 is a Thursday and is counted in SA and the NT (and in NSW, Tasmania and the ACT, where it is an ordinary weekday).

This page is about those statutory payment-schedule, notice-of-dispute and payment due dates. It is different from the [Christmas–New Year 2026/27 working days guide](/guides/christmas-shutdown-working-days-2026/), which is about ordinary working days, public holidays and industry shutdowns for programmes and EOT notices.

The tables use the same counting rules as the free [Australia Security of Payment calculator](/tools/security-of-payment-calculator/) and the eight jurisdiction calculators: [NSW](/tools/nsw-security-of-payment-calculator/), [VIC](/tools/vic-security-of-payment-calculator/), [QLD](/tools/qld-security-of-payment-calculator/), [WA](/tools/wa-security-of-payment-calculator/), [SA](/tools/sa-security-of-payment-calculator/), [TAS](/tools/tas-security-of-payment-calculator/), [ACT](/tools/act-security-of-payment-calculator/) and [NT](/tools/nt-security-of-payment-calculator/). Use those tools for any other service date. For a plain working-day count (not the SOP rules), use the [working days calculator](/tools/working-days-calculator/) or the [free working days calendar (Excel)](/).

**General information only, not legal advice.** Missing a payment schedule or notice of dispute deadline can have serious consequences, including liability for the claimed amount. A contract can set an earlier time in many jurisdictions, but cannot push a date later than a statutory cap where the Act sets one. The tables use the statutory defaults (and, for the ACT, the 15 business day cap). Confirm the current authorised Act and the official holiday list before you rely on a date.

## Default payment schedule or notice of dispute deadlines

| Claim served, given or received | NSW schedule 10 BD | VIC schedule 10 BD after service | QLD schedule 15 BD | WA schedule 15 BD | SA schedule 15 BD | TAS applicable day 10 BD / 20 BD residential | ACT schedule 10 BD | NT notice of dispute 10 WD (implied) |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| Friday 20 November 2026 | 4 Dec 2026 | 4 Dec 2026 | 11 Dec 2026 | 11 Dec 2026 | 11 Dec 2026 | 7 Dec 2026 / 21 Dec 2026 | 4 Dec 2026 | 4 Dec 2026 |
| Monday 30 November 2026 | 14 Dec 2026 | 14 Dec 2026 | 21 Dec 2026 | 21 Dec 2026 | 21 Dec 2026 | 14 Dec 2026 / 5 Jan 2027 | 14 Dec 2026 | 14 Dec 2026 |
| Tuesday 1 December 2026 | 15 Dec 2026 | 15 Dec 2026 | 11 Jan 2027 | 11 Jan 2027 | 22 Dec 2026 | 15 Dec 2026 / 7 Jan 2027 | 15 Dec 2026 | 15 Dec 2026 |
| Friday 4 December 2026 | 18 Dec 2026 | 18 Dec 2026 | 14 Jan 2027 | 14 Jan 2027 | 4 Jan 2027 | 18 Dec 2026 / 12 Jan 2027 | 18 Dec 2026 | 18 Dec 2026 |
| Friday 11 December 2026 | 4 Jan 2027 | 14 Jan 2027 | 21 Jan 2027 | 21 Jan 2027 | 11 Jan 2027 | 4 Jan 2027 / 19 Jan 2027 | 4 Jan 2027 | 8 Jan 2027 |
| Monday 14 December 2026 | 5 Jan 2027 | 15 Jan 2027 | 22 Jan 2027 | 22 Jan 2027 | 12 Jan 2027 | 5 Jan 2027 / 20 Jan 2027 | 5 Jan 2027 | 11 Jan 2027 |
| Friday 18 December 2026 | 11 Jan 2027 | 21 Jan 2027 | 29 Jan 2027 | 29 Jan 2027 | 18 Jan 2027 | 12 Jan 2027 / 27 Jan 2027 | 11 Jan 2027 | 15 Jan 2027 |
| Monday 21 December 2026 | 12 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 19 Jan 2027 | 13 Jan 2027 / 28 Jan 2027 | 12 Jan 2027 | 18 Jan 2027 |
| Wednesday 23 December 2026 | 14 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 21 Jan 2027 | 15 Jan 2027 / 1 Feb 2027 | 14 Jan 2027 | 20 Jan 2027 |
| Thursday 24 December 2026 | 15 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 15 Jan 2027 | 21 Jan 2027 |
| Friday 25 December 2026 | 15 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 15 Jan 2027 | 21 Jan 2027 |
| Monday 28 December 2026 | 15 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 15 Jan 2027 | 21 Jan 2027 |
| Thursday 31 December 2026 | 15 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 15 Jan 2027 | 21 Jan 2027 |
| Monday 4 January 2027 | 18 Jan 2027 | 22 Jan 2027 | 1 Feb 2027 | 1 Feb 2027 | 25 Jan 2027 | 19 Jan 2027 / 3 Feb 2027 | 18 Jan 2027 | 21 Jan 2027 |

## Default or statutory payment due dates

| Claim served, given or received | NSW due 15 BD principal→head / 20 BD head→sub | VIC default due 10 BD after earliest claimable day | QLD default due 10 BD if the contract is silent | WA due 20 BD principal→head / 25 BD sub (or principal, no head) | SA default due 15 BD if silent | TAS default due same as the applicable day: 10 / 20 BD | ACT due 15 BD statutory cap | NT default due 20 WD if silent |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| Friday 20 November 2026 | 11 Dec 2026 / 18 Dec 2026 | 16 Nov 2026 earliest 31 Oct 2026; on or before service | 4 Dec 2026 | 18 Dec 2026 / 14 Jan 2027 | 11 Dec 2026 | 7 Dec 2026 / 21 Dec 2026 | 11 Dec 2026 | 18 Dec 2026 |
| Monday 30 November 2026 | 21 Dec 2026 / 5 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026 | 14 Dec 2026 | 15 Jan 2027 / 22 Jan 2027 | 21 Dec 2026 | 14 Dec 2026 / 5 Jan 2027 | 21 Dec 2026 | 11 Jan 2027 |
| Tuesday 1 December 2026 | 22 Dec 2026 / 6 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026 | 15 Dec 2026 | 18 Jan 2027 / 25 Jan 2027 | 22 Dec 2026 | 15 Dec 2026 / 7 Jan 2027 | 22 Dec 2026 | 12 Jan 2027 |
| Friday 4 December 2026 | 4 Jan 2027 / 11 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026 | 18 Dec 2026 | 21 Jan 2027 / 29 Jan 2027 | 4 Jan 2027 | 18 Dec 2026 / 12 Jan 2027 | 4 Jan 2027 | 15 Jan 2027 |
| Friday 11 December 2026 | 11 Jan 2027 / 18 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026 | 14 Jan 2027 | 29 Jan 2027 / 5 Feb 2027 | 11 Jan 2027 | 4 Jan 2027 / 19 Jan 2027 | 11 Jan 2027 | 22 Jan 2027 |
| Monday 14 December 2026 | 12 Jan 2027 / 19 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026; on or before service | 15 Jan 2027 | 1 Feb 2027 / 8 Feb 2027 | 12 Jan 2027 | 5 Jan 2027 / 20 Jan 2027 | 12 Jan 2027 | 25 Jan 2027 |
| Friday 18 December 2026 | 18 Jan 2027 / 25 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026; on or before service | 21 Jan 2027 | 5 Feb 2027 / 12 Feb 2027 | 18 Jan 2027 | 12 Jan 2027 / 27 Jan 2027 | 18 Jan 2027 | 1 Feb 2027 |
| Monday 21 December 2026 | 19 Jan 2027 / 27 Jan 2027 | 14 Dec 2026 earliest 30 Nov 2026; on or before service | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 19 Jan 2027 | 13 Jan 2027 / 28 Jan 2027 | 19 Jan 2027 | 2 Feb 2027 |
| Wednesday 23 December 2026 | 21 Jan 2027 / 29 Jan 2027 | 22 Jan 2027 earliest 22 Dec 2026 | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 21 Jan 2027 | 15 Jan 2027 / 1 Feb 2027 | 21 Jan 2027 | 4 Feb 2027 |
| Thursday 24 December 2026 | 22 Jan 2027 / 1 Feb 2027 | 22 Jan 2027 earliest 22 Dec 2026 | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 22 Jan 2027 | 5 Feb 2027 |
| Friday 25 December 2026 | 22 Jan 2027 / 1 Feb 2027 | 22 Jan 2027 earliest 22 Dec 2026 | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 22 Jan 2027 | 5 Feb 2027 |
| Monday 28 December 2026 | 22 Jan 2027 / 1 Feb 2027 | 22 Jan 2027 earliest 22 Dec 2026 | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 22 Jan 2027 | 5 Feb 2027 |
| Thursday 31 December 2026 | 22 Jan 2027 / 1 Feb 2027 | 22 Jan 2027 earliest 22 Dec 2026 | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 22 Jan 2027 | 18 Jan 2027 / 2 Feb 2027 | 22 Jan 2027 | 5 Feb 2027 |
| Monday 4 January 2027 | 25 Jan 2027 / 2 Feb 2027 | 22 Jan 2027 earliest 22 Dec 2026 | 22 Jan 2027 | 8 Feb 2027 / 15 Feb 2027 | 25 Jan 2027 | 19 Jan 2027 / 3 Feb 2027 | 25 Jan 2027 | 5 Feb 2027 |

## Easy-to-miss December rules

- **Victoria’s default due date is not counted from the day you actually served the claim.** If the contract is silent, payment is due 10 business days after the earliest day a claim may be served for that progress payment (s 12(1)(b)). Serving late does not push that date out, so a mid-December claim for November work can already be due. The due-date table assumes the most recent period already claimable on the service date: last day of the named month for January–November work; 22 December for work from 1–21 December; 31 January for work from 22–31 December (s 14A). A claim served before that earliest day is still valid but is taken to have been served on the earliest day, and the payment-schedule clock starts then (s 14A(5)). If the contract sets a due date, it is capped at 20 business days after effective service (s 12(1B)). The tables use the silent-contract default, not that cap.
- **Western Australia starts the clock on the day the claim is given, even if that day is not a business day.** The day of giving is business day 0; the next business day is day 1. The Supreme Court of Western Australia applied that approach to a Saturday claim in _Martinus Rail Pty Ltd v Co-operative Bulk Handling Ltd_ [2025] WASC 373. A claim given inside the 22 December–10 January window still starts on that day, so 11 January is day 1. The Act applies to contracts entered into on or after 1 August 2022.
- **The Northern Territory uses a notice of dispute, not a payment schedule.** If the contract is silent, the implied notice-of-dispute deadline is 10 working days after the claim is received, and payment is due 20 working days after receipt (s 20 and Sch 1 cl 6). A term putting payment later than 30 working days after the claim is read as 30 working days (s 13). 24 December 2026 (a Thursday) is a working day, because a part-day public holiday does not stop the day being a working day (s 4(b)). The dates above are territory-wide, with no regional show day — and no show day falls in this December–January window.
- **The ACT 15 business day due date is a cap, not only a fallback if the contract is silent** (s 13(1)). The table shows that statutory latest date. If the contract has an earlier due date, that earlier date applies.
- **Tasmania treats regional statutory holidays as statewide exclusions** for SOP counting (s 4A(2)), including show days, both Regatta and Recreation Day, Agfest, Launceston Cup and the part-day Devonport Cup. Easter Tuesday is counted. If the contract is silent, the payment due date is the same applicable day as the payment schedule: 10 business days, or 20 business days where the claim relates to a residential structure, the respondent is the owner of the land and is not a building practitioner (s 15(2) and s 19(3)).
- **Queensland’s table uses the 10 business day default** that applies when the contract is silent (s 73(1)(b)). Commercial building contracts and construction management trade contracts or subcontracts also have QBCC Act caps of 15 and 25 business days (QBCC Act ss 67W and 67U). An earlier contract date still applies. The Brisbane Royal Queensland Show holiday is in August, so it does not move these December dates. The calculator starts the count from the date entered; the QBCC’s own holiday guidance takes a more cautious view of claims given on the last business day before Christmas — check that guidance and the [Queensland calculator](/tools/qld-security-of-payment-calculator/) notes before you rely on a 21 December claim date.

## How the days are counted on this page

- The day the claim is served, given or received is day 0. The next business day (or, in the NT, working day) is day 1. If that calendar day is a weekend, a public holiday or a day in the Christmas exclusion, it is skipped until the next countable day.
- Weekends are never counted. Public holidays are the statewide (or, for the NT, territory-wide) holidays already used on the calculator pages. Local-only holidays are not excluded, except that Tasmania applies statutory holidays statewide for SOP purposes.
- These are the statutory defaults. Enter an earlier contract time in the relevant calculator if your contract shortens a period. Do not use a later date than a cap the Act sets.

## Sources

The counting rules and holiday lists are the ones already used on the calculators, drawn from the current authorised Acts and official holiday tables cited there:

- NSW: _Building and Construction Industry Security of Payment Act 1999_, [NSW legislation](https://legislation.nsw.gov.au/view/html/inforce/current/act-1999-046); holidays from [nsw.gov.au](https://www.nsw.gov.au/about-nsw/public-holidays) (checked 6 November 2026).
- VIC: _Building and Construction Industry Security of Payment Act 2002_, as amended from 15 April 2026, [Authorised Version 015](https://www.legislation.vic.gov.au/in-force/acts/building-and-construction-industry-security-payment-act-2002/015); holidays from [business.vic.gov.au](https://business.vic.gov.au/business-information/public-holidays) (checked 6 November 2026).
- QLD: _Building Industry Fairness (Security of Payment) Act 2017_, [Queensland legislation](https://www.legislation.qld.gov.au/view/html/inforce/current/act-2017-043); holidays from [qld.gov.au](https://www.qld.gov.au/recreation/travel/holidays/public) (checked 6 November 2026).
- WA: _Building and Construction Industry (Security of Payment) Act 2021_, Official Version 00-f0-00 (current from 21 October 2026), [WA legislation](https://www.legislation.wa.gov.au/legislation/statutes.nsf/law_a147300.html); holidays from [wa.gov.au](https://www.wa.gov.au/service/employment/workplace-arrangements/public-holidays-western-australia) (checked 6 November 2026).
- SA: _Building and Construction Industry Security of Payment Act 2009_, authorised Version 10.12.2011, [SA legislation](https://www.legislation.sa.gov.au/lz?path=/c/a/building%20and%20construction%20industry%20security%20of%20payment%20act%202009); holidays from [SafeWork SA](https://www.safework.sa.gov.au/resources/public-holidays) (checked 6 November 2026).
- TAS: _Building and Construction Industry Security of Payment Act 2009_, authorised as at 1 July 2025, [Tasmanian legislation](https://www.legislation.tas.gov.au/view/html/inforce/current/act-2009-086); statutory holidays as at 9 October 2026, matching [WorkSafe Tasmania](https://worksafe.tas.gov.au/topics/laws-and-compliance/public-holidays) (checked 14 November 2026).
- ACT: _Building and Construction Industry (Security of Payment) Act 2009_, Republication No 14 (effective 6 December 2025), [ACT legislation register](https://legislation.act.gov.au/a/2009-50/); holidays from the [ACT Government tables](https://www.act.gov.au/living-in-the-act/public-holidays-school-terms-and-daylight-saving) (checked 14 November 2026), plus the August bank holiday under the Holidays Act 1958.
- NT: _Construction Contracts (Security of Payments) Act 2004_, as in force at 25 May 2024, [NT legislation register](https://legislation.nt.gov.au/Legislation/CONSTRUCTION-CONTRACTS-SECURITY-OF-PAYMENTS-ACT-2004); holidays from the [NT Government tables](https://nt.gov.au/nt-public-holidays) (checked 15 November 2026).

Run another date in the [Australia Security of Payment calculator](/tools/security-of-payment-calculator/), or grab the [free AU working days calendar](/) (Excel and PDF for NSW, VIC, QLD, WA and SA). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.