# How to write a construction variation that actually gets paid

Most variations that get knocked back fail on paperwork, not merit. The work was real, the instruction was real, and the cost was real — but the notice was late, the scope was vague, there was no price until the final claim, or nobody can find the direction in writing. Here is a practical routine Australian contractors can use to keep variations recoverable.

## 1. Find your contract’s variation clause first

Every contract sets its own rules for who can direct a variation, how fast you must give notice, and what the notice must contain. In AS 4000 the variations machinery sits around clause 36; AS 2124 and many bespoke / minor-works contracts use different numbering and different time bars. Read the clause once at the start of the job and write three things on the cover of your register:

- who can issue a direction (superintendent, principal, client’s agent),
- the notice period in working days,
- whether pricing must be agreed before the work starts.

If your special conditions amend the standard form, those amendments win. Do not assume “industry practice” overrides a time bar.

## 2. Get the direction in writing — the same day

Verbal instructions on site are normal. Recoverable variations are not built on memory. If a direction comes verbally, confirm it the same day by email or site instruction:

- who gave it,
- the time and place,
- what was asked (and what was _not_ asked),
- that you treat it as a variation direction under the contract clause.

A one-line confirmation sent that afternoon beats a perfect claim written three months later. Attach a photo or marked-up drawing if it helps pin the scope.

## 3. Describe the change, not the whole job

A good variation notice is short and specific. Aim for:

- a unique reference (V-001, V-002…),
- what changed compared with the contract documents (drawing numbers and revisions, specification clauses, set-out),
- why it changed (client request, latent condition, design error, authority requirement, design development),
- the cost, split into labour, materials, plant, subcontractors and margin,
- the time impact in **working days**, if any,
- any supporting dockets, quotes or photos.

Vague phrases like “extra works as directed” invite rejection. Tie every dollar and every day back to a document or a measurable quantity.

## 4. Price it before you do it, where you can

Agreeing the price up front avoids the end-of-job argument. Where the work cannot wait:

- say so in the notice,
- proceed under the contract’s daywork / schedule-of-rates machinery if it exists,
- keep signed dockets daily,
- issue a priced claim as soon as the quantities settle.

Unpriced variations that sit open until practical completion are the ones that get trimmed. Pricing discipline is as important as notice discipline.

## 5. Keep one register (and close the loop)

Track every variation in one place with a clear status:

- notified,
- priced,
- approved,
- rejected / disputed,
- invoiced,
- paid.

Totals per status tell you, at a glance, how much money is sitting unapproved. Link each entry to the related RFI, site instruction and programme activity so an EOT claim and a money claim stay consistent. When a variation is rejected, record the reason and the next step — reissue, negotiation, or formal dispute path under the contract.

## 6. Working days, not calendar days

Time impacts belong in working days unless your contract says otherwise. Public holidays, RDOs and Christmas shutdown change the arithmetic. If you claim “five days” over Easter without checking the state holiday list, you will overstate or understate the delay. Use the correct state calendar (NSW, VIC, QLD, WA or SA) and note which calendar you used in the claim.

## 7. Common failure modes to avoid

- Notice sent after the contractual time bar.
- Direction never confirmed in writing.
- Scope that describes the whole trade instead of the delta.
- Price with no breakdown.
- Time claim with no link to the programme.
- Variations buried in a progress claim with no separate notice history.
- Using the wrong state’s public holidays when converting calendar delays to working days.

## Template pack

The Builder Admin AU **Variation & RFI Register Pack** (Excel) is set up for Australian contractors: variation register with status totals, notice / pricing fields, RFI log, and room to link documents. It is designed to sit beside a working-days calendar and a site diary so notice, evidence and time stay in one system.

Paid packs are coming soon on Gumroad (builderadminau.gumroad.com). Until then, grab the free multi-state working-days calendar:

**Free download (instant):** [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/)

Or email **dede.hart@bundillabeef.com**.

_General information only — not legal advice. Always follow the terms of your own contract and get professional advice where the amount or risk justifies it._

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.