# What to record in a site diary (and why it saves you in a dispute)

A site diary is the cheapest insurance on a construction job. When a delay claim, defect argument, latent-condition fight or safety incident comes up months later, the diary written on the day is usually the most believable record anyone has — provided it is factual, contemporaneous and complete enough to reconstruct what happened.

Australian contractors often treat the diary as a chore. The ones who get paid for delays treat it as evidence collection.

## Record these every day

### Date, weather and site conditions

Rain, heat, wind and wet ground are the backbone of most weather EOTs. Note start/stop times if work was interrupted, and whether the site was accessible. “Wet” without times is weak; “rain 06:30–10:15, slab pour aborted, crew stood down” is usable.

### Labour on site

Your own crew and each subcontractor, with head counts and hours. If a trade did not turn up, say so. Attendance gaps often explain programme slip better than any narrative.

### Plant and deliveries

What arrived, what was missing, what was rejected, and any stand-down of plant. Crane and concrete delays are classic claim and counter-claim territory — the diary should show the booking, the arrival window and what actually happened.

### Work done

Short and specific, by area or level (“L2 slab poured, grid A–D”; “frame complete Unit 12”). Avoid slogans like “progress as planned” — they help nobody when the programme is later scrutinised.

### Delays and disruptions

What stopped work, from when to when, who was affected, and who was notified. Link the entry to the programme activity ID if you have one. Separately log whether an EOT notice went out the same day.

### Directions and visitors

Instructions from the client, superintendent, certifier, inspector or designer — and who gave them. If it sounds like a variation, cross-reference the variation register and confirm in writing.

### Safety and quality

Toolbox talks, incidents, near misses, inspections, NCRs and hold-point releases. These protect people first; they also protect the company when someone later alleges the site was uncontrolled.

### Photos

Dated photos tied to the diary entry beat paragraphs of description. Keep filenames or a photo log that matches the diary date.

## Habits that make a diary count in a dispute

1. **Write it the same day.** Back-filled diaries are easy to challenge. If the supervisor finishes at 4 pm, the entry should exist before they leave site.
2. **Keep it factual.** Save opinions (“lazy subbie”, “hopeless design”) for a separate internal note. The diary should read like a neutral log.
3. **Have the supervisor sign or initial each entry.** Electronic sign-off is fine if the system timestamps it.
4. **Link delays to the programme and variation register.** A lost day that never appears in an EOT notice or variation claim is often a lost day forever.
5. **Use working days consistently.** When you summarise weekly lost time, count Monday–Friday excluding public holidays for the state you are in. A “five-day” delay that swallows a public holiday is not five productive days.
6. **Store it where it can be found.** Cloud folder, project drive or bound book — pick one system and keep copies. A perfect diary in a vanished notebook helps no one.

## Weekly roll-up

Once a week, summarise:

- total labour hours by trade,
- working days available vs worked,
- delays in working days,
- open variations / RFIs raised from diary events,
- outstanding deliveries and inspections.

The weekly summary is what project managers actually read; the daily page is what tribunals and lawyers test.

## NSW and multi-state context

Record-keeping expectations show up in contracts, WHS duties and security-of-payment practice across Australia. The _content_ of a good diary is similar in NSW, Victoria, Queensland, WA and South Australia; the _calendar_ behind delay counts is not. Use the correct state public-holiday list when you convert interruptions into working days, and note which state calendar you used.

## Template

The Builder Admin AU **Site Diary & Daily Report Pack** (Excel + PDF) includes a daily diary, weekly summary, labour and plant logs, and a delay register that totals lost working days. Pair it with the free multi-state working-days calendar so holiday arithmetic stays honest.

Paid packs are coming soon on Gumroad (builderadminau.gumroad.com). For the free calendar pack (NSW, VIC, QLD, WA, SA — Excel + PDF):

**Free download (instant):** [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/)

Or email **dede.hart@bundillabeef.com**.

_General information only. Check your contract and any safety or record-keeping rules that apply to your job. This is not legal or WHS advice._

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.