# ACT Security of Payment calculator

Enter the date a payment claim was given in the Australian Capital Territory and this works out the latest day for a payment schedule and the statutory due date for the progress payment under the _Building and Construction Industry (Security of Payment) Act 2009_ (ACT). It counts business days the way the Act and the Legislation Act 2001 define them: not a Saturday or Sunday; not a public holiday or bank holiday in the ACT; and not 27, 28, 29, 30 or 31 December. The calculator follows the current authorised SOP Act on the ACT legislation register (Republication No 14, effective 6 December 2025) and the Legislation Act dictionary (Republication No 126, effective 23 February 2026).

## The timeframes this uses

- **Payment schedule:** the respondent becomes liable to pay the claimed amount on the due date if no payment schedule is provided within the earlier of the time the contract requires and 10 business days after the payment claim is given (section 16(4)). There is no different window for a head contract and a subcontract.
- **Due date for payment:** a progress payment is payable on the earlier of 15 business days after the payment claim is given, or the day it becomes payable under the contract (section 13(1)). The 15 business day period is a maximum, not only a fallback if the contract is silent. That rule has applied to progress claims given on or after 11 March 2024, including under contracts already on foot, following the _Building and Construction Legislation Amendment Act 2023_ (see the [ACT Government security of payments page](https://www.planning.act.gov.au/professionals/building-regulatory-system/practitioner-regulation/security-of-payments)). This tool shows that statutory 15 business day date. If the contract has an earlier due date, that earlier date applies.

## How the days are counted

- The day the claim is given is business day 0. The next business day is day 1. That follows section 151 of the _Legislation Act 2001_: a period described as beginning after a stated day, act or event does not include that day.
- 27–31 December are never business days under the SOP Act dictionary, even when they are not otherwise public holidays or bank holidays.
- If a claim is given on a weekend, a public holiday, a bank holiday or a day in that 27–31 December window, the clock still starts on the day you enter. The next business day is day 1. The Act does not treat the claim as first given on the following business day. Whether the claim was actually given on that day can still depend on how it was sent (see the Legislation Act, part 19.5, as noted in the SOP Act).
- The first Monday in August is a bank holiday under section 4(1)(b) of the _Holidays Act 1958_ (Republication No 11, effective 1 January 2018). Because the Legislation Act definition of business day excludes bank holidays as well as public holidays, that Monday is not counted here, even though it is not a public holiday.
- Public holiday dates for 2026–2028 are taken from the [ACT Government public holidays tables](https://www.act.gov.au/living-in-the-act/public-holidays-school-terms-and-daylight-saving) (checked 14 November 2026), including Canberra Day, Reconciliation Day, and the additional weekdays listed when Anzac Day, Christmas Day, Boxing Day or New Year’s Day fall on a weekend. Some of those additional days (for example the Monday after Anzac Day in 2026, when 25 April is a Saturday) are declared days on the official list, not automatic under section 3(1)(a) of the Holidays Act alone.

## Things to check before you rely on a date

- The Act does not apply to a construction contract for insurable residential building work if a resident owner is a party, to the extent the contract relates to a building where that person lives or intends to live. A person who is or should be licensed as an owner-builder is not a resident owner for that exclusion (section 9(2)(b) and (7)). It also does not apply to construction work carried out outside the ACT, or to a contract entered into before the commencement of part 2 (section 9).
- A payment claim may be given only before the later of the period in the contract and 12 months after the work was last carried out or the goods and services were last supplied (section 15(5)). This tool does not check that window, or the monthly claiming rules in section 15(4) and (6).
- This is a counting tool, not legal advice. Missing a payment schedule deadline can leave you liable for the full claimed amount, so get advice on anything disputed. Check the current Act on the [ACT legislation register](https://legislation.act.gov.au/a/2009-50/), and the [ACT Government security of payments guidance](https://www.planning.act.gov.au/professionals/building-regulatory-system/practitioner-regulation/security-of-payments).

Start with the [Australia Security of Payment calculator](/tools/security-of-payment-calculator/) to compare all eight jurisdictions. For worked December 2026 payment-claim deadlines, see the [December 2026 Security of Payment deadlines guide](/guides/december-2026-security-of-payment-deadlines/). Building in another state? Use the [NSW](/tools/nsw-security-of-payment-calculator/), [VIC](/tools/vic-security-of-payment-calculator/), [QLD](/tools/qld-security-of-payment-calculator/), [WA](/tools/wa-security-of-payment-calculator/), [SA](/tools/sa-security-of-payment-calculator/) or [TAS](/tools/tas-security-of-payment-calculator/) or [NT](/tools/nt-security-of-payment-calculator/) Security of Payment calculators. For plain working-day counts in NSW, VIC, QLD, WA and SA use the [working days calculator](/tools/working-days-calculator/), or grab the [free working days calendar (Excel)](/).

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.