# NT Security of Payment calculator

Enter the date a payment claim was received in the Northern Territory and this works out the implied deadline for a notice of dispute, the implied due date for payment if the contract is silent, and the statutory latest date under the _Construction Contracts (Security of Payments) Act 2004_ (NT). It counts working days the way section 4 of the Act defines them: not a Saturday or Sunday; not a public holiday in the place in which the relevant act is to be done or may be done (other than a public holiday that is part of a day); and not a day in the period beginning on 25 December and ending on 7 January. The calculator follows the current authorised Act on the NT legislation register (as in force at 25 May 2024, checked 15 November 2026).

## The timeframes this uses

- **Notice of dispute (implied term):** if the contract has no written provision about when and how a party must respond to a payment claim, a notice of dispute must be given within 10 working days after receiving the claim, and any undisputed amount must be paid in that same time (section 20(a) and Schedule 1, clause 6(2)(a)). The Territory Act uses a notice of dispute, not an East Coast-style payment schedule.
- **Payment due if the contract is silent:** if the contract has no written provision about by when a payment must be made, the whole claimed amount must be paid within 20 working days after receiving the claim (section 20(b) and Schedule 1, clause 6(2)(b)). There is no different default for a head contract and a subcontract.
- **Statutory maximum:** a contract term that would make payment due more than 30 working days after the payment is claimed is read as requiring payment within 30 working days after it is claimed (section 13). This tool always shows that 30 working day date. If you enter a contract period, it is capped at 30 working days.

## How the days are counted

- The day the claim is received (or claimed, for section 13) is working day 0. The next working day is day 1. That follows section 28(1) of the _Interpretation Act 1978_ (as in force at 21 April 2023): a period dating from a given day, act or event is reckoned exclusive of that day. The same Act, and sections 4 to 8 of the SOP Act, apply to the implied terms (SOP Act section 25). Section 28(3) of the SOP Act uses the same “day after” starting point for the 65 working day adjudication window.
- 25 December to 7 January inclusive are never working days under section 4, even when they are not otherwise public holidays. That window is longer than the 27–31 December exclusion in NSW, SA, Tasmania and the ACT, and it includes New Year’s Day and the first week of January.
- If a claim is received on a weekend, a public holiday or a day in that 25 December–7 January window, the clock still starts on the day you enter. The next working day is day 1. The Act does not treat the claim as first received on the following working day. Whether the claim was actually received on that day can still depend on how it was sent.
- Christmas Eve and New Year’s Eve are part-day public holidays (7pm to midnight). Section 4(b) says a public holiday that is part of a day does not stop that day being a working day, so 24 December is counted when it is a weekday and falls before the shutdown window. 31 December is already excluded by the 25 December–7 January rule.
- Anzac Day is 25 April, or the following Monday if 25 April falls on a Sunday. There is no additional weekday when Anzac Day falls on a Saturday (as it does in 2026). Additional weekdays listed when Christmas Day, Boxing Day or New Year’s Day fall on a weekend sit inside the shutdown window, so they do not change the count.
- Public holiday dates for 2026–2028 are taken from the [NT Government public holidays tables](https://nt.gov.au/nt-public-holidays) (checked 15 November 2026). Choose a show region if the relevant act is to be done in that region: Alice Springs, Tennant Creek, Katherine, Darwin and Borroloola each have their own show day, and section 4(b) only excludes a public holiday “in the place in which any relevant act is to be done or may be done”. That place may be the site or where the notice or payment has to be given. Leave the selector on territory-wide only if no show day applies.

## Things to check before you rely on a date

- The implied 10 and 20 working day rules apply only where the contract has no written provision about that matter (section 20). If the contract already says when a response is due or when payment is due, those written terms apply, subject to the section 13 cap of 30 working days after the claim.
- A payment dispute arises if the claim is rejected or wholly or partly disputed, or if the amount has not been paid in full when it is due (section 8). A party then has 65 working days after the dispute arises to apply for adjudication, and the first day of that period is the day after the dispute arises (section 28(1) and (3)). This tool does not calculate that 65 working day date, because when the dispute arises depends on when a notice is given or when payment falls due under the contract.
- The Act applies to a construction contract entered into after it commenced, whether the contract is written or oral, and wherever it was entered into (section 9). It does not apply to the extent a party is a prescribed employee under a Fair Work award or agreement (section 9(3)), or to a contract prescribed by the Regulations. Parties to a high value construction contract may in some cases agree to contract out of adjudication (section 10A).
- This is a counting tool, not legal advice. Missing a notice of dispute or payment deadline can open the way to adjudication, so get advice on anything disputed. Check the current Act on the [NT legislation register](https://legislation.nt.gov.au/Legislation/CONSTRUCTION-CONTRACTS-SECURITY-OF-PAYMENTS-ACT-2004).

Start with the [Australia Security of Payment calculator](/tools/security-of-payment-calculator/) to compare all eight jurisdictions. For worked December 2026 payment-claim deadlines, see the [December 2026 Security of Payment deadlines guide](/guides/december-2026-security-of-payment-deadlines/). Building in another state or territory? Use the [NSW](/tools/nsw-security-of-payment-calculator/), [VIC](/tools/vic-security-of-payment-calculator/), [QLD](/tools/qld-security-of-payment-calculator/), [WA](/tools/wa-security-of-payment-calculator/), [SA](/tools/sa-security-of-payment-calculator/), [TAS](/tools/tas-security-of-payment-calculator/) or [ACT](/tools/act-security-of-payment-calculator/) Security of Payment calculators. For plain working-day counts in NSW, VIC, QLD, WA and SA use the [working days calculator](/tools/working-days-calculator/), or grab the [free working days calendar (Excel)](/).

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.