# Queensland Security of Payment calculator (BIF Act)

Enter the date a payment claim was given in Queensland and this works out the latest day for a payment schedule and the due date for the progress payment under the _Building Industry Fairness (Security of Payment) Act 2017_ (Qld). It counts business days the way the Act defines them: not a Saturday, Sunday or public holiday, and not any day from 22 December to 10 January.

## The timeframes this uses

- **Payment schedule:** if you don't intend to pay the full claim by the due date, give a payment schedule within the time the contract requires or 15 business days after the claim is given, whichever ends first (section 76).
- **Due date when the contract is silent:** 10 business days after the payment claim is made (section 73(1)(b)).
- **Commercial building contracts:** a clause allowing payment later than 15 business days after the claim is void (QBCC Act section 67W).
- **Construction management trade contracts and subcontracts:** a clause allowing payment later than 25 business days after the claim is void (QBCC Act section 67U).
- If your contract sets an earlier due date, the contract date applies. Residential contracts with home owners have their own rules.

## Things to check before you rely on a date

- The whole period from 22 December to 10 January is excluded, not just the public holidays. A claim given in that window is treated as given on the first business day after it.
- The QBCC's own holiday guidance takes a cautious view that a claim given on the last business day before Christmas is also counted from the first business day in January. The [QBCC business days page](https://qbcc.qld.gov.au/resources/news/business-days-holiday-period-security-payment) sets this out.
- Show holidays differ by region. Only the Brisbane Royal Queensland Show day is built in; tick the box if it applies where the work is.
- This is a counting tool, not legal advice. Missing a payment schedule deadline can leave you liable for the full claimed amount and open to QBCC disciplinary action, so get advice on anything disputed. Check the current Act on the [Queensland legislation site](https://www.legislation.qld.gov.au/view/html/inforce/current/act-2017-043).

Start with the [Australia Security of Payment calculator](/tools/security-of-payment-calculator/) to compare all eight jurisdictions. For worked December 2026 payment-claim deadlines, see the [December 2026 Security of Payment deadlines guide](/guides/december-2026-security-of-payment-deadlines/). Building in another state? Use the [NSW](/tools/nsw-security-of-payment-calculator/), [VIC](/tools/vic-security-of-payment-calculator/), [WA](/tools/wa-security-of-payment-calculator/), [SA](/tools/sa-security-of-payment-calculator/) or [TAS](/tools/tas-security-of-payment-calculator/) or [ACT](/tools/act-security-of-payment-calculator/) or [NT](/tools/nt-security-of-payment-calculator/) Security of Payment calculators. For plain working-day counts in NSW, VIC, QLD, WA and SA use the [working days calculator](/tools/working-days-calculator/), or grab the [free working days calendar (Excel)](/).

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.