# Australia Security of Payment calculator

Security of payment timeframes are set by each Australian state and territory, not by a single national Act. Choose a jurisdiction to open that calculator and work out a payment schedule, notice of dispute or due date from the date the claim was served, given or received. The date counting stays in the individual calculators, which follow the authorised legislation cited on each page.

This is a free guide and counting hub, not legal advice. Missing a payment schedule, notice of dispute or payment deadline can have serious consequences, including liability for the claimed amount. Use the calculator for your jurisdiction and check the current authorised Act before you rely on a date.

You can also jump from the table below. Each cell is a short statement of the rule used in that jurisdiction’s calculator — open the page for the full wording, sources and the date tool.

## Payment claim timeframes compared

| Jurisdiction | Payment schedule / response | Default or statutory due date | Christmas / New Year exclusion | Easy-to-miss rules |
| --- | --- | --- | --- | --- |
| [NSW](/tools/nsw-security-of-payment-calculator/) New South Wales | 10 business days after the claim is served, or earlier if the contract requires (s 14). A contract can shorten this but not lengthen it. | 15 business days after the claim is made, principal to head contractor (s 11(1A)); 20 business days, head contractor to a subcontractor or supplier (s 11(1B)); or earlier if the contract says so. | 27–31 December are never business days (s 4), even when they are not otherwise public holidays. | Owner-occupier residential construction contracts are exempt and are not covered by the calculator. The Fair Trading and Building Legislation Amendment Bill 2026 proposes renaming “business day” to “working day” with the same days excluded — check the current Act. |
| [VIC](/tools/vic-security-of-payment-calculator/) Victoria | 10 business days after effective service, or earlier if the contract requires (s 15(4)). | If the contract is silent, 10 business days after the earliest day a claim may be served for that progress payment — not after actual service (s 12(1)(b)). If the contract sets a due date, a term putting payment later than 20 business days after the claim is served has no effect (s 12(1B)). | 22 December to 10 January inclusive are never business days (s 4). | The calculator is for claims served on or after 15 April 2026. Section 14A sets when a claim may first be served (generally the last day of the named month; 22 December for work from 1–21 December; 31 January for work from 22–31 December). A claim served early is taken to have been served on that earliest day. Only public holidays observed throughout Victoria are skipped. The Friday before the AFL Grand Final is included for 2026 but not for 2027 or 2028, because those dates had not been gazetted when the holiday list was checked. |
| [QLD](/tools/qld-security-of-payment-calculator/) Queensland | 15 business days after the claim is given, or earlier if the contract requires (s 76). | 10 business days after the claim is made if the contract is silent (s 73(1)(b)). QBCC Act caps: a clause allowing payment later than 15 business days is void for commercial building contracts (QBCC Act s 67W); later than 25 business days is void for construction management trade contracts and subcontracts (QBCC Act s 67U). An earlier contract date still applies. | 22 December to 10 January inclusive are never business days. A claim given in that window is treated as given on the first business day after it. | The QBCC’s holiday guidance takes a cautious view that a claim given on the last business day before Christmas is also counted from the first business day in January — see the Queensland calculator. Show holidays differ by region; only the Brisbane Royal Queensland Show (Ekka) is built into the calculator, behind a checkbox. Residential contracts with home owners have their own rules. |
| [WA](/tools/wa-security-of-payment-calculator/) Western Australia | 15 business days after the payment claim is made, or earlier if the contract requires (s 25(1)). | 20 business days, principal to head contractor (s 20(1)(a)); 25 business days, to a subcontractor or a principal where there is no head contractor (s 20(1)(b)); 10 business days default for home building work if the contract is silent (s 20(3)(b)). Earlier contract dates apply for the 20 and 25 business day pathways. | 22 December to 10 January inclusive are never business days (s 4). | The day the claim is given is business day 0; the next business day is day 1, including where the claim is given on a weekend, public holiday or a day in the Christmas window (Martinus Rail Pty Ltd v Co-operative Bulk Handling Ltd [2025] WASC 373). Older contracts sit under the previous Construction Contracts Act regime. The 2028 Show Day is omitted because it is still to be confirmed by proclamation. Some regional areas observe King’s Birthday on a different date. |
| [SA](/tools/sa-security-of-payment-calculator/) South Australia | 15 business days after the claim is served, or earlier if the contract requires (s 14(4)). | 15 business days after the claim is made if the contract is silent (s 11(1)(b)). If the contract has an express due date, that date applies (s 11(1)(a)). Unlike some other jurisdictions, section 11 does not set a maximum number of business days. | 27–31 December are never business days (s 4). | Part-day Christmas Eve and New Year’s Eve (7pm to midnight) are counted as business days (Legislation Interpretation Act 2021 s 46). The Act does not apply to domestic building work on premises the other party lives in or proposes to live in (s 7). From 1 September 2026, regulation 7 of the 2026 Regulations exempts a party to a Crown contract worth more than $4,000,000 excluding GST from the no-schedule consequence in s 14(4) and from the adjudication provisions. |
| [TAS](/tools/tas-security-of-payment-calculator/) Tasmania | The earlier of the period in which payment is required under the contract and the applicable day — or, where the claim relates to a residential structure, the respondent is the owner of the land and is not a building practitioner, the later of those two periods (s 19(2)). The applicable day is 10 business days after service, or 20 business days in that residential-owner case (s 19(3)). | If the contract is silent, payment becomes due and payable before the expiry of that same applicable day: 10 business days, or 20 business days in the residential-owner case (s 15(2)). If the contract has an express due date, that date applies (s 15(1)). | 27–31 December are never business days (s 4A). | Section 4A(2) applies statutory holidays statewide and for the whole day, so regional show days, both Regatta and Recreation Day, Agfest, Launceston Cup and the part-day Devonport Cup are excluded everywhere in Tasmania. Easter Tuesday (Statutory Holidays Act s 6 only) is counted. Easter Sunday is included from 2027. Unlike some other states, the Act does apply to residential building work (with the longer applicable day in the case above). |
| [ACT](/tools/act-security-of-payment-calculator/) Australian Capital Territory | 10 business days after the claim is given, or earlier if the contract requires (s 16(4)). There is no different window for a head contract and a subcontract. | The earlier of 15 business days after the claim is given and the day it becomes payable under the contract (s 13(1)). The 15 business day period is a statutory cap, not only a default if the contract is silent. That rule has applied to progress claims given on or after 11 March 2024. | 27–31 December are never business days (SOP Act dictionary). | Business days also exclude ACT public holidays and bank holidays. The first Monday in August is a bank holiday under Holidays Act 1958 s 4(1)(b) and is therefore not a business day. The Act does not apply to certain resident-owner insurable residential building work (s 9). |
| [NT](/tools/nt-security-of-payment-calculator/) Northern Territory | The Territory Act uses a notice of dispute, not an East Coast-style payment schedule. If the contract is silent, a notice of dispute must be given within 10 working days after the claim is received, and any undisputed amount must be paid in that same time (s 20 and Sch 1 cl 6). | If the contract is silent, the claimed amount must be paid within 20 working days after the claim is received (s 20 and Sch 1 cl 6). A contract term that would make payment due more than 30 working days after the claim is read as 30 working days (s 13). There is no different default for a head contract and a subcontract. | 25 December to 7 January inclusive are never working days (s 4). That window is longer than the 27–31 December exclusion in NSW, SA, Tasmania and the ACT, and it includes New Year’s Day and the first week of January. | The Act counts working days, not business days. Part-day Christmas Eve and New Year’s Eve are counted (s 4(b)); 24 December 2026 (a Thursday) is therefore a working day. Anzac Day has no additional weekday when 25 April is a Saturday (as in 2026). Optional show-region selector for Alice Springs, Tennant Creek, Katherine, Darwin and Borroloola — those days are public holidays only in that place. |

## Things to check before you rely on a date

- Most East Coast-style Acts count **business days**. The Northern Territory counts **working days** and uses a notice of dispute rather than a payment schedule.
- Christmas and New Year exclusions are not the same everywhere: 27–31 December in NSW, SA, Tasmania and the ACT; 22 December to 10 January in Victoria, Queensland and Western Australia; 25 December to 7 January in the Northern Territory. See the [Christmas–New Year 2026/27 working days guide](/guides/christmas-shutdown-working-days-2026/). For default December 2026 claim dates across all eight jurisdictions, see the [December 2026 Security of Payment deadlines guide](/guides/december-2026-security-of-payment-deadlines/).
- South Australia counts part-day Christmas Eve and New Year’s Eve; the Northern Territory also counts those part-day holidays, though 31 December already sits inside its shutdown window. Tasmania applies regional statutory holidays statewide for SOP counting.
- When the clock starts can depend on how the claim was served, given or received, and on whether it arrived after hours or on a non-business day. Each calculator explains the starting rule it uses. If in doubt, assume the earliest date and get advice on anything disputed.
- Check the current authorised legislation for the jurisdiction. The individual calculator pages link the official register and, where used, the official holiday tables.

## The eight calculators

- [**NSW** — Building and Construction Industry Security of Payment Act 1999 (NSW)](/tools/nsw-security-of-payment-calculator/)
- [**VIC** — Building and Construction Industry Security of Payment Act 2002 (Vic), as amended from 15 April 2026](/tools/vic-security-of-payment-calculator/)
- [**QLD** — Building Industry Fairness (Security of Payment) Act 2017 (Qld)](/tools/qld-security-of-payment-calculator/)
- [**WA** — Building and Construction Industry (Security of Payment) Act 2021 (WA), Official Version 00-f0-00 (current from 21 October 2026), contracts entered into on or after 1 August 2022](/tools/wa-security-of-payment-calculator/)
- [**SA** — Building and Construction Industry Security of Payment Act 2009 (SA), authorised Version 10.12.2011](/tools/sa-security-of-payment-calculator/)
- [**TAS** — Building and Construction Industry Security of Payment Act 2009 (Tas), authorised as at 1 July 2025](/tools/tas-security-of-payment-calculator/)
- [**ACT** — Building and Construction Industry (Security of Payment) Act 2009 (ACT), Republication No 14 (effective 6 December 2025)](/tools/act-security-of-payment-calculator/)
- [**NT** — Construction Contracts (Security of Payments) Act 2004 (NT), as in force at 25 May 2024](/tools/nt-security-of-payment-calculator/)

For a plain working-day count in NSW, VIC, QLD, WA and SA (not the SOP business-day or working-day rules above), use the [working days calculator](/tools/working-days-calculator/), or grab the [free working days calendar (Excel)](/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.