# Western Australia Security of Payment calculator

Enter the date a payment claim was given in Western Australia and this works out the latest day for a payment schedule and the due date for the progress payment under the _Building and Construction Industry (Security of Payment) Act 2021_ (WA). It counts business days the way section 4 of the Act defines them: not a Saturday, Sunday or public holiday, and not any day from 22 December to 10 January (inclusive). The calculator follows Official Version 00-f0-00 (current from 21 October 2026) and applies to construction contracts entered into on or after 1 August 2022.

## The timeframes this uses

- **Payment schedule:** the respondent may give a payment schedule before the earlier of the time the contract requires and 15 business days after the payment claim is made (section 25(1)). If no schedule is given in time, the respondent becomes liable to pay the claimed amount on the due date (section 26).
- **Principal to head contractor:** payment is due 20 business days after the payment claim is made, unless the contract sets an earlier date (section 20(1)(a) and (2)).
- **Subcontractor, or a principal where there is no head contractor:** payment is due 25 business days after the payment claim is made, unless the contract sets an earlier date (section 20(1)(b) and (2), including the note to section 20(1)).
- **Home building work:** if the contract provides a due date, that date applies; if it does not, payment is due 10 business days after the payment claim is made (section 20(3)). This pathway is only the default where the contract is silent.

## How the days are counted

- A Western Australian government user guide states that, for counting business days, the day a document is given is business day 0. The next business day is day 1.
- The whole period from 22 December to 10 January is excluded, not just Christmas, Boxing Day and New Year’s Day.
- If a claim is given on a weekend, a public holiday or a day in that Christmas window, the clock still starts on the day the claim was given. The next business day is day 1. The Supreme Court of Western Australia applied that approach to a claim given on a Saturday in _Martinus Rail Pty Ltd v Co-operative Bulk Handling Ltd_ [2025] WASC 373. The Act does not treat the claim as first given on the following business day.
- Statewide public holidays for 2026–2028 are taken from the WA Government list used in the [WA working days guide](/guides/wa-working-days-2027/) (checked 6 November 2026). Some regional areas observe King’s Birthday on a different date. The 2028 Show Day listed on that calendar is not included here, because it is still to be confirmed by proclamation; if it is later gazetted as a public holiday where the work is, the count may move.

## Things to check before you rely on a date

- The Act applies to construction contracts entered into on or after 1 August 2022. Older contracts sit under the previous Construction Contracts Act regime.
- If your contract sets an earlier due date than the statutory 20 or 25 business days, the contract date applies. A later contractual date does not.
- Home building work has its own due-date rule, including where the contract does provide a date. This tool only calculates the 10 business day default for when the contract is silent.
- Whether a claim has actually been “given” can depend on how it was sent (for example email or post) and on the regulations about when a document is taken to have been given. This tool starts from the date you enter.
- This is a counting tool, not legal advice. Missing a payment schedule deadline can leave you liable for the full claimed amount, so get advice on anything disputed. Check the current Act on the [Western Australian legislation site](https://www.legislation.wa.gov.au/legislation/statutes.nsf/law_a147300.html), and the government’s [Security of Payment guidance](https://www.wa.gov.au/government/multi-step-guides/subcontractor-payment-disputes-security-of-payment-act).

Start with the [Australia Security of Payment calculator](/tools/security-of-payment-calculator/) to compare all eight jurisdictions. For worked December 2026 payment-claim deadlines, see the [December 2026 Security of Payment deadlines guide](/guides/december-2026-security-of-payment-deadlines/). Building in another state? Use the [NSW](/tools/nsw-security-of-payment-calculator/), [VIC](/tools/vic-security-of-payment-calculator/), [QLD](/tools/qld-security-of-payment-calculator/), [SA](/tools/sa-security-of-payment-calculator/) or [TAS](/tools/tas-security-of-payment-calculator/) or [ACT](/tools/act-security-of-payment-calculator/) or [NT](/tools/nt-security-of-payment-calculator/) Security of Payment calculators. For plain working-day counts in NSW, VIC, QLD, WA and SA use the [working days calculator](/tools/working-days-calculator/), or grab the [free working days calendar (Excel)](/).

**Free AU Working Days Calendar 2026–2028** — Excel + PDF for NSW, VIC, QLD, WA and SA.

[Download free calendar](/free-working-days-calendar.zip) [Email me the pack](mailto:dede.hart@bundillabeef.com?subject=Builder%20Admin%20AU%20-%20calendar%20download)

Or open the live page: [https://builder-admin-au-calendar-c35dcb.deed.page/](https://builder-admin-au-calendar-c35dcb.deed.page/). Paid tender, programme, variation/RFI and site diary packs are coming soon on Gumroad.